Modelling setup times in project scheduling

Authors

[ 1 ] Instytut Informatyki (II), Wydział Informatyki i Zarządzania, Politechnika Poznańska | [ P ] employee

Year of publication

2006

Chapter type

chapter in monograph

Publication language

english

Keywords
EN
  • project scheduling
  • setup
  • setup time
  • setup cost
Abstract

EN In this chapter project scheduling problems with setup times are considered. Some practical applications justifying considering setups separately from activities are described. An extensive classification of setup times adapted from machine scheduling is proposed, including activity vs. class setup, separable vs. inseparable setup, as well as sequence-independent and sequence-dependent setup times. A new category of setup times - schedule-dependent ones - is discussed. The main part of the paper shows how to model setup times in the presence of particular project components, such as: precedence constraints, resource availability constraints, multiple resource units requests, multiple resources, etc. Some possible extensions of the presented models are given.

Pages (from - to)

131 - 166

DOI

10.1007/978-0-387-33768-5_6

URL

https://link.springer.com/chapter/10.1007/978-0-387-33768-5_6

Book

Perspectives in modern project scheduling

This website uses cookies to remember the authenticated session of the user. For more information, read about Cookies and Privacy Policy.