Analysis of the Impact of Changeover Time and Priority Rules on the Timely Execution of Customer Orders

Authors

[ 1 ] Instytut Technologii Materiałów, Wydział Inżynierii Mechanicznej, Politechnika Poznańska | [ P ] employee

Scientific discipline (Law 2.0)

[2.9] Mechanical engineering

Year of publication

2022

Chapter type

chapter in monograph / paper

Publication language

english

Keywords
EN
  • priority rules
  • production scheduling
  • computer simulation
Abstract

EN The article is the preliminary research results determining the influence of selected criteria on the timeliness of customer orders, the workstation load and the required size of the finished products warehouse. The criteria included in this paper are the changeover time and the priority rule. The literature analysis covers issues related to the priority rules and machine changeover. The following part of the work presents the adopted research methodology, production process model and input data. Production plans were prepared successively and 9 model variants were designated, with different changeover times and priority rules applied. The work also simulated the production process in the FlexSim program, using previously prepared production plans. For the evaluation of the models, a summary of the obtained results was taken into account, showing the timely execution of customer orders, the workstation load and the required size of the finished products warehouse. The article ended with conclusions, in which a variant was indicated, in which a combination of factors allows to achieve the highest punctuality of order fulfillment, the smallest size of the warehouse and the optimal load of workstations (the shortest inactivity, the longest implementation of the production process).

Date of online publication

24.06.2021

Pages (from - to)

12 - 24

DOI

10.1007/978-3-030-78170-5_2

URL

https://link.springer.com/chapter/10.1007/978-3-030-78170-5_2

Book

Innovations in Industrial Engineering

Presented on

International Conference Innovation in Engineering, ICIE 2021, 28-30.06.2021, Guimarães, Portugal

Ministry points / chapter

20

This website uses cookies to remember the authenticated session of the user. For more information, read about Cookies and Privacy Policy.